  • Toledo Edison viewed site and sent drawings as to proposed placement of transformer.

  • Site Crew removed all light polls, 4 each placed at northwest corner of site to be used elsewhere, per request of owner.

  • Demo of light pole bases, existing utility boxes, existing fence columns.