Floor poured on office side. Rooms starting to take shape | Voda - Orland Park, IL
- Mar 22, 2020
- 0 min
Construction Progress | Voda - Orland Park, IL
- Mar 15, 2020
- 0 min
Masons and Laborers working thru the Saturday Weather | Voda - Orland Park, IL
- Mar 14, 2020
- 0 min
Brick going up. Really coming to life | Voda - Orland Park, IL
- Mar 4, 2020
- 0 min
Precast roof deck is up. Mason's putting up stone now | Voda - Orland Park, IL
- Feb 29, 2020
- 0 min
North wall done. East tower up. Looking forward to warmer days ahead | Voda - Orland Park, IL
- Feb 23, 2020
- 0 min
Moving on Up! North Wall going up and tower one starting to take shape | Voda - Orland Park, IL
- Feb 22, 2020
- 0 min
Up-Up & Away! Traffic for Dayssss | Voda - Orland Park, IL
- Feb 19, 2020
- 0 min
Moving along. South walls done. Working on north wall | Voda - Orland Park, IL
- Feb 18, 2020
- 0 min
Pushing through the Winter! | Voda - Orland Park, IL
- Feb 6, 2020
- 1 min
Laying Block Walls | Voda - Orland Park, IL
- Feb 5, 2020
- 1 min
Ready to Start Laying Block Walls | Voda - Orland Park, IL
- Jan 19, 2020
- 0 min
Construction Progress | Voda - Orland Park, IL
- Jan 15, 2020
- 0 min
Foundations | Voda - Orland Park, IL
- Jan 11, 2020
- 0 min
Pouring Foundation in January | Voda - Orland Park, IL
- Jan 3, 2020
- 0 min
Footings! | Voda - Orland Park, IL
- Dec 31, 2019
- 0 min
Footings Being Installed for Pour | Voda - Orland Park, IL
- Dec 30, 2019
- 0 min
- Dec 29, 2019
- 0 min
Under Ground Work | Voda - Orland Park, IL
- Dec 28, 2019
- 0 min
Construction Progress Video | Voda - Orland Park, IL